Response Planning is the responsibility of the functional areas and considersA mitigation.B deflection.C contingency planning.D unforeseen occurrences.E All of the above.

题目

Response Planning is the responsibility of the functional areas and considers

A mitigation.

B deflection.

C contingency planning.

D unforeseen occurrences.

E All of the above.


相似考题
更多“Response Planning is the responsibility of the functional areas and considersA mitigation.B deflection.C contingency planning.D unforeseen occurrences.E All of the above.”相关问题
  • 第1题:

    Which of the following planning considerations is often overlooked?

    A.Planning for project termination.

    B.Qualified project manager assignment.

    C.Insuring top management support.

    D.Clearly defined tasks.

    E.All of the above.


    正确答案:A
    A

  • 第2题:

    Planning activities such that predetermined resource availability pools are not exceeded is called:

    A.Resource leveling.

    B.Manpower leveling.

    C.Resource limited planning.

    D.Manpower planning.

    E.Manpower contingency planning.


    正确答案:C
    C

  • 第3题:

    Satisfaction of the functional requirements of a product is called _____ .

    A . usability

    B . reliability

    C . maintainability

    D . producibility

    E . All of the above.


    正确答案:E

  • 第4题:

    A team may not be fully functional until each member

    A seeks consensus in decision making

    B feels personal acceptance

    C depends on the team leader for direction

    D A and B.

    E All of the above.


    正确答案:D

  • 第5题:

    Range estimating in determining cost risk probabilities requires _____ .

    A an amount of financial exposure.

    B risks and opportunities ranked in order of bottom line importance

    C contingency requirements for expected level of confidence

    D probability of cost overrun occurrences

    E All of the above.


    正确答案:E

  • 第6题:

    Management reserve is generally intended to be used to:

    A implement additional unbudgeted scope

    B compensate for inaccurate estimates

    C cover major unforeseen catastrophes

    D cover unforeseen problems in the project

    E All of the above.


    正确答案:D

  • 第7题:

    1 Contingency planning should include all but which of the following?

    A. The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

    B the development of schedule alternatives and work-around

    C. the management of a contingency budget

    D. an assessment of project shut-down liabilities.

    E. A and C


    正确答案:A

  • 第8题:

    93 Response Planning is the responsibility of the functional areas and considers

    A. mitigation.

    B. deflection.

    C. contingency planning.

    D. unforeseen occurrences.

    E. All of the above


    正确答案:E

  • 第9题:

    161 Which of the following planning considerations is often overlooked?

    A. Planning for project termination.

    B. Qualified project manager assignment.

    C. Insuring top management support.

    D. Clearly defined tasks.

    E. All of the above.


    正确答案:A

  • 第10题:

    ● Interfacing with the customer after project go-ahead is the responsibility of:

    A Project sponsor

    B Project team

    C Project manager

    D Functional manager

    E All of the above are possible, based upon the size and complexity of the project


    正确答案:C

  • 第11题:

    ● The document authorizing functional areas to charge against the project is the:

    A Work authorization form

    B Scope baseline

    C Project charter

    D Management plan

    E Linear responsibility chart


    正确答案:A

  • 第12题:

    ● The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A The scope baseline.

    B Scope authorization

    C Scope definition

    D Scope planning.

    E All of the above.


    正确答案:D

  • 第13题:

    The process of choosing/documenting the best approach to achieve the project objectives is part of:

    A.The scope baseline.

    B.Scope authorization

    C.Scope definition

    D.Scope planning.

    E.All of the above.


    正确答案:D
    D

  • 第14题:

    Managerial Reserves are:

    A.allowances to account for price changes that can occur over the life of a project.

    B.incentive fees paid to managers for good performance.

    C.funds used to offset poor cost or schedule estimates.

    D.accounts to allocate and maintain funds for contingency programs

    E.All of the above.


    正确答案:D

    D

  • 第15题:

    The auditing function that provides feedback about the quality of output is referred to as:

    A . quality control.

    B . quality planning.

    C . quality assurance.

    D . quality improvement

    E . All of the above.


    正确答案:C

  • 第16题:

    The main player in project communication is the

    A sponsor

    B project manager

    C functional manager

    D functional team

    E All of the above.


    正确答案:B

  • 第17题:

    Contingency planning should include all but which of the following?

    A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

    B the development of schedule alternatives and work-around

    C the management of a contingency budget

    D an assessment of project shut-down liabilities.

    E A and C


    正确答案:A

  • 第18题:

    78 The process of choosing/documenting the best approach to achieve the project objectives is part of: A. The scope baseline.

    B. Scope authorization

    C. Scope definition

    D. Scope planning.

    E. All of the above.


    正确答案:D

  • 第19题:

    61 The document authorizing functional areas to charge against the project is the:

    A. Work authorization form.

    B. Scope baseline

    C. Project charter

    D. Management plan

    E. Linear responsibility chart


    正确答案:A

  • 第20题:

    142 Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

    A. The project manager

    B. The functional manager

    C. The project sponsor

    D. The client

    E. All of the above


    正确答案:A

  • 第21题:

    ● During the planning phase of a project, you realize that more than one functional department possesses the skill and technical know-how to perform. a given task. The best way for the project manager to handle this would be to:

    A Make the decision, document it in the linear responsibility chart, and distribute the chart to all departments.

    B Let the affected line groups decide among themselves who will perform. the work

    C Ask the executive sponsor to make the decision

    D Allow each line group to perform. part of the task

    E All of the above


    正确答案:B

  • 第22题:

    ● Ensuring that all work is both authorized and funded by contractual documentation is the responsibility of:

    A The project manager

    B The functional manager

    C The project sponsor

    D The client

    E All of the above


    正确答案:A

  • 第23题:

    ● Which of the following planning considerations is often overlooked?

    A Planning for project termination.

    B Qualified project manager assignment.

    C Insuring top management support.

    D Clearly defined tasks.

    E All of the above.


    正确答案:A