更多“Which method shown below is acceptable for reducing cost or shortening the schedule?A."Crashing"B.Changing scope.C.Performing activities in parallel rather than in series.D.All of the above.E.A and C only.”相关问题
  • 第1题:

    Scheduling is the process by which decisions are made concerning:

    A.Tasks to be accomplished.

    B.Personnel/organization that will be assigned to accomplish the task.

    C.Time when the tasks are to be completed.

    D.All of the above.

    E.A and C only.


    正确答案:E
    E

  • 第2题:

    A Project Status Report would include all of the following except:

    A Cost and schedule reports

    B Changes to scope. cost or schedule

    C Narrative explanation of variances

    D Personnel problems on the project

    E Upcoming activities


    正确答案:D

  • 第3题:

    32 History has shown that project managers can be trained in a combination of ways. Which method is usually preferred by most companies?

    A. Experiential learning, on-the-job

    B. Formal education and special course (degreed programs)

    C. Professional activities, seminars

    D. Individual readings

    E. None of the above


    正确答案:A

  • 第4题:

    95 A Project Status Report would include all of the following except:

    A. Cost and schedule reports

    B. Changes to scope. cost or schedule

    C. Narrative explanation of variances

    D. Personnel problems on the project

    E. Upcoming activities


    正确答案:D

  • 第5题:

    ● Which of the following are types of status reports?

    A document, variance, trend and exception

    B cost, trend, schedule and acquisition

    C cost, schedule, technical performance

    D analysis, cost, performance and schedule

    E All of the above.


    正确答案:C

  • 第6题:

    The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).

    A.the project is ahead of its planned schedule

    B.less work was completed than was planned

    C.the cost overrun for work completed

    D.the cost under-run of performance to date


    正确答案:B
    此题主要考查挣值分析法的相关概念,它综合了范围、时间和成本数据,主要用于实际成本的绩效测量。基本思想是通过测量和计算已完成工作的预算费用与已完成工作的实际费用,将其与计划工作预算费用相比较得到项目的费用偏差,从而达到判断项目成本和进度计划执行情况,来帮助项目管理团队分析项目的完成情况,衡量项目的成本效率,为成本控制提供依据。挣值分析法主要涉及到3个参数,4个指标。其中3个参数如下:?计划工作量的预算成本(PV),已完成工作量的预算成本(EV),已完成工作量的实际成本(AC)?4个指标是指CV,SV,CPI,SPI:进度偏差(SV)是项目进度绩效的一种指标。成本偏差(CV)是项目成本绩效的一种指标。进度绩效指数(SPI)是比较项目已完成进度与计划进度的一种指标。当SPI小于1.0时,说明已完成的工作量未达到计划要求;当SPI大于1.0时,则说明已完成的工作量超过计划。SPI等于EV与PV的比值。公式:SPI=EV/PV。成本绩效指数(CPI)是比较已完成工作的价值与实际成本的一种指标。它考核已完成工作的成本效率。当CPI小于1.0时,说明已完成工作的成本超支;当CPI大于1.0时,则说明到目前为止成本有结余。CPI等于EV与AC的比值。公式:CPI=EV/AC。

  • 第7题:

    Schedule compression shortens the project schedule without changing the project scope, to meet schedule constraints, imposed dates, or other schedule objectives. Schedule compression techniques include crashing and ( )

    A.fast tracking

    B.what-if scenario analysis

    C.resource leveling

    D.critical chain method


    正确答案:A

  • 第8题:

    Establishing a project(74)involves listen mile stones,activities,and deliverables with intend start and finish dates of which the scheduling of employees may be an element.

    A.cost management plan
    B.risk management
    C.scope management plan
    D.management schedule

    答案:D
    解析:
    翻译:建立项目进度管理计划涉及里程碑,活动和可交付成果的开始和完成日期,人力资源日历也属于其中一种元素。A、成本管理计划 B、风险管理计划C、范围管理计划 D、进度管理计划

  • 第9题:

    The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().

    A.the project is a head of its planned schedule
    B.less work was completed than was planned
    C.the cost overrun for work completed
    D.the cost under-run of performance to date

    答案:B
    解析:
    挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余

  • 第10题:

    ( )techniques are used to find ways to bring project activities that are alignment with the plan by fast tracking or crashing the schedule for the remaining work.

    A.Schedule forecasts
    B.Schedule compression
    C.Change requests
    D.Data analysis

    答案:B
    解析:
    翻译:( )技术用于通过快速跟踪或崩溃剩余工作的计划来找到使落后的项目活动与计划保持一致的方法。A、进度预测 B、进度压缩 C、变更请求 D、数据分析

  • 第11题:

    Which two are characteristics of the cost-containment business challenge?()

    • A、reducing security breaches
    • B、using the Internet more
    • C、reducing upgrade charges
    • D、adopting new applications and services

    正确答案:C,D

  • 第12题:

    单选题
    Sub-cooling is a method of reducing the temperature of the liquid refrigerant below its ().
    A

    freezing point

    B

    floc point

    C

    condensing temperature

    D

    compression temperature


    正确答案: D
    解析: 暂无解析

  • 第13题:

    History has shown that project managers can be trained in a combination of ways. Which method is usually preferred by most companies?

    A . Experiential learning, on-the-job

    B . Formal education and special course (degreed programs)

    C . Professional activities, seminars

    D . Individual readings

    E . None of the above


    正确答案:A

  • 第14题:

    199 Which method shown below is acceptable for reducing cost or shortening the schedule? A. "Crashing"

    B. Changing scope.

    C. Performing activities in parallel rather than in series.

    D. All of the above.

    E. A and C only


    正确答案:D

  • 第15题:

    57 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above.


    正确答案:C

  • 第16题:

    139 Which of the following are types of status reports?

    A. document, variance, trend and exception

    B. cost, trend, schedule and acquisition

    C. cost, schedule, technical performance

    D. analysis, cost, performance and schedule

    E. All of the above


    正确答案:C

  • 第17题:

    The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned


    正确答案:C
    挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

  • 第18题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intendstart and finish dates^of which the scheduling of employees may be an element.

    A.cost management plan

    B.risk management

    C.scope management plan

    D.management schedule


    正确答案:D

  • 第19题:

    Sub-cooling is a method of reducing the temperature of the liquid refrigerant below its ______.

    A.freezing point

    B.floc point(浊点)

    C.condensing temperature

    D.compression temperature


    正确答案:C

  • 第20题:

    Establishing a project ( ) involves listen milestones, activities, and deliverables with intended start and finish dates, of which the scheduling of employees may be an element


    A.cost management plan
    B.risk management plan
    C.soope management plan
    D.management schedule


    答案:D
    解析:

  • 第21题:

    Which of the following activities is NOT typical of the Task-Based Language Teaching method?

    A.Problem-solving activities.
    B.Opinion exchange activities.
    C.Information-gap activities.
    D.Pattern practice activities.

    答案:D
    解析:
    本题考查任务型语言教学活动。题干的意思:下列哪项活动不是典型的任务型语言教学活动任务型语言教学是指在教学活动中,教师围绕特定的交际和语言项目,设计出具体的、可操作的任务,学生通过表达、沟通、交涉、解释、询问等各种语言活动形式来完成任务,以达到学习和掌握语言的目的。根据任务的定义及特点,任务型教学活动可分为解决问题型、交流意见型、信息沟等类型的活动。D项“句型练习活动”属于传统的教学活动,不属于典型的任务型语言教学活动。故本题选D。

  • 第22题:

    Schedule compression shortens the project schedule without changing the project scope,to meet schedule constraints,imposed dates,or other schedule objectives.Schedule compression techniques include crashing and( ).

    A.fast tracking
    B.what-if scenario analysis
    C.resource leveling
    D.critical chain methoD.

    答案:A
    解析:
    进度压缩技术包括赶工和快速跟进。(74) A.快速跟进 B.假设情景分析 C.资源平衡 D.关键链法

  • 第23题:

    单选题
    Which of the following activities is NOT typical of the Task-based Language Teaching Method?
    A

    Problem-solving activities.

    B

    Opinion exchange activities.

    C

    Information-gap activities.

    D

    Pattern practice activities.


    正确答案: A
    解析: