第1题:
The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.
A . Unauditable.
B . Undistributed.
C . Preauthorized.
D . Contingency.
E . In-process.
第2题:
Risks that cannot be identified or evaluated _____ .
A should be deflected to the contracting officer.
B should be handled via contingency allowances.
C should be ignored, since they cannot be identified.
D should be ignored, since they are not covered in the Risk Assessment.
E C and D
第3题:
Response Planning is the responsibility of the functional areas and considers
A mitigation.
B deflection.
C contingency planning.
D unforeseen occurrences.
E All of the above.
第4题:
The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .
A Is accomplished by paying the actual costs to the contractor.
B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C Is an undisclosed contingency in the contractor's bid.
D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E B and C
第5题:
93 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .
A. Is accomplished by paying the actual costs to the contractor.
B. Is accomplished by paying the contractor for his costs plus a fixed fee (profit).
C. Is an undisclosed contingency in the contractor's bid.
D. Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.
E. B and C
第6题:
1 Contingency planning should include all but which of the following?
A. The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.
B the development of schedule alternatives and work-around
C. the management of a contingency budget
D. an assessment of project shut-down liabilities.
E. A and C
第7题:
145 Risks that cannot be identified or evaluated _____ .
A. should be deflected to the contracting officer.
B. should be handled via contingency allowances.
C. should be ignored, since they cannot be identified.
D. should be ignored, since they are not covered in the Risk Assessment.
E. C and D
第8题:
●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.
(74) A. Contingency reserve
B. Project profit
C. Management reserve
D. Special fund
第9题:
对Contingency通常:()
第10题:
对一项在发生之前未界定的风险事件作出响应称作:()
第11题:
Operation security requires the implementation of physical security to con-trol which of the following? 操作安全要求对下列哪项实施物理安全控制?()
第12题:
缓和风险响应。(risk mitigation response)
权变措施。(workaround response)
纠正行动。(corrective action response)
应急响应。(contingency response)
第13题:
There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.
A . Management reserve, unplanned allowance fund.
B . Management reserve, contingency.
C . Contingency fund, management reserve.
D . Unplanned allowance fund, budgetary reserve.
E . Unplanned reserve, planned reserve.
第14题:
Range estimating in determining cost risk probabilities requires _____ .
A an amount of financial exposure.
B risks and opportunities ranked in order of bottom line importance
C contingency requirements for expected level of confidence
D probability of cost overrun occurrences
E All of the above.
第15题:
Contingency planning should include all but which of the following?
A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.
B the development of schedule alternatives and work-around
C the management of a contingency budget
D an assessment of project shut-down liabilities.
E A and C
第16题:
Risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):
A should be deflected to the contracting officer
B should be handled via contingency allowances
C should be ignored, since they cannot be identified
D should be ignored, since they are not covered in the Project Risk Assessment
E C and D
第17题:
127 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.
A. Unauditable.
B. Undistributed.
C. Preauthorized.
D. Contingency.
E. In-process
第18题:
93 Response Planning is the responsibility of the functional areas and considers
A. mitigation.
B. deflection.
C. contingency planning.
D. unforeseen occurrences.
E. All of the above
第19题:
A.This process assigns cost estimates to project activities including risks and contingency plans.
B.The cost baseline will be used to measure variances and future project performance.
C.This process assigns cost estimates for expected future period operating costs.
D.The cost baseline is the expected cost for the project.
第20题:
第21题:
You are working on the cost budget for one project. Which of the following is true()
第22题:
Delay due to port congestion,pilots,tugs not available is a:()
第23题:
This process assigns cost estimates to project activities including risks and contingency plans.
The cost baseline will be used to measure variances and future project performance.
This process assigns cost estimates for expected future period operating costs.
The cost baseline is the expected cost for the project.