  • 第1题:

    The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.

    A . Unauditable.

    B . Undistributed.

    C . Preauthorized.

    D . Contingency.

    E . In-process.


    正确答案:B

  • 第2题:

    Risks that cannot be identified or evaluated _____ .

    A should be deflected to the contracting officer.

    B should be handled via contingency allowances.

    C should be ignored, since they cannot be identified.

    D should be ignored, since they are not covered in the Risk Assessment.

    E C and D


    正确答案:B

  • 第3题:

    Response Planning is the responsibility of the functional areas and considers

    A mitigation.

    B deflection.

    C contingency planning.

    D unforeseen occurrences.

    E All of the above.


    正确答案:E

  • 第4题:

    The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .

    A Is accomplished by paying the actual costs to the contractor.

    B Is accomplished by paying the contractor for his costs plus a fixed fee (profit).

    C Is an undisclosed contingency in the contractor's bid.

    D Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.

    E B and C


    正确答案:C

  • 第5题:

    93 The type of contract (payment mechanism) chosen for a project is often a reflection of the degree of risk associated with completing that project. For a firm fixed price contract, payment for risk _____ .

    A. Is accomplished by paying the actual costs to the contractor.

    B. Is accomplished by paying the contractor for his costs plus a fixed fee (profit).

    C. Is an undisclosed contingency in the contractor's bid.

    D. Is accomplished by paying for the budgeted costs of dealing with risks, as predicted in the project risk assessment.

    E. B and C


    正确答案:C

  • 第6题:

    1 Contingency planning should include all but which of the following?

    A. The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

    B the development of schedule alternatives and work-around

    C. the management of a contingency budget

    D. an assessment of project shut-down liabilities.

    E. A and C


    正确答案:A

  • 第7题:

    145 Risks that cannot be identified or evaluated _____ .

    A. should be deflected to the contracting officer.

    B. should be handled via contingency allowances.

    C. should be ignored, since they cannot be identified.

    D. should be ignored, since they are not covered in the Risk Assessment.

    E. C and D


    正确答案:B

  • 第8题:

    ●The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope.(74) could provide the fund to cover the newly discovered work item.

    (74) A. Contingency reserve

    B. Project profit

    C. Management reserve

    D. Special fund


    正确答案:C

  • 第9题:

    对Contingency通常:()

    • A、不必制定应变计划;
    • B、应制定应变计划;
    • C、视严重程度决定是否制定;
    • D、船长决定。

    正确答案:B

  • 第10题:

    对一项在发生之前未界定的风险事件作出响应称作:()

    • A、缓和风险响应。(risk mitigation response)
    • B、权变措施。(workaround  response)
    • C、纠正行动。(corrective  action response)
    • D、应急响应。(contingency response)

    正确答案:B

  • 第11题:

    Operation security requires the implementation of physical security to con-trol which of the following? 操作安全要求对下列哪项实施物理安全控制?()

    • A、evacuation procedures 撤离步骤
    • B、incoming hardware 硬件搬入
    • C、contingency conditions 应急条件
    • D、unauthorized personnel access 未经授权的人员访问

    正确答案:D

  • 第12题:

    单选题
    对一项在发生之前未界定的风险事件作出响应称作:()
    A

    缓和风险响应。(risk mitigation response)

    B

    权变措施。(workaround  response)

    C

    纠正行动。(corrective  action response)

    D

    应急响应。(contingency response)


    正确答案: D
    解析: 暂无解析

  • 第13题:

    There are two major types of reserves used on projects. The _____ is for (usually major) scope changes that were not considered as part of the original plan, whereas the _____ is to compensate for minor changes in estimating, escalation factors.

    A . Management reserve, unplanned allowance fund.

    B . Management reserve, contingency.

    C . Contingency fund, management reserve.

    D . Unplanned allowance fund, budgetary reserve.

    E . Unplanned reserve, planned reserve.


    正确答案:C

  • 第14题:

    Range estimating in determining cost risk probabilities requires _____ .

    A an amount of financial exposure.

    B risks and opportunities ranked in order of bottom line importance

    C contingency requirements for expected level of confidence

    D probability of cost overrun occurrences

    E All of the above.


    正确答案:E

  • 第15题:

    Contingency planning should include all but which of the following?

    A The development of a contingency allowance determined by combining (layering) various estimate segments to form. larger estimate segments.

    B the development of schedule alternatives and work-around

    C the management of a contingency budget

    D an assessment of project shut-down liabilities.

    E A and C


    正确答案:A

  • 第16题:

    Risk classified as unknown unknowns (i.e., those which cannot be identified or evaluated):

    A should be deflected to the contracting officer

    B should be handled via contingency allowances

    C should be ignored, since they cannot be identified

    D should be ignored, since they are not covered in the Project Risk Assessment

    E C and D


    正确答案:B

  • 第17题:

    127 The budget associated with scope changes that have been approved but not planned for yet, is referred to a(n) _____ budget.

    A. Unauditable.

    B. Undistributed.

    C. Preauthorized.

    D. Contingency.

    E. In-process


    正确答案:B

  • 第18题:

    93 Response Planning is the responsibility of the functional areas and considers

    A. mitigation.

    B. deflection.

    C. contingency planning.

    D. unforeseen occurrences.

    E. All of the above


    正确答案:E

  • 第19题:

    You are working on the cost budget for one project. Which of the following is true()

    A.This process assigns cost estimates to project activities including risks and contingency plans.

    B.The cost baseline will be used to measure variances and future project performance.

    C.This process assigns cost estimates for expected future period operating costs.

    D.The cost baseline is the expected cost for the project.


    参考答案:B

  • 第20题:

    The project budget has been finalized.Additional work has been discovered that was not planned for in the budget or project scope. (74) could provide the fund to cover the newly discovered work item.

    A.Contingency reserve
    B.Project profit
    C.Management reserve
    D.Special fund

    答案:C
    解析:
    项目的预算还未最终确定,额外的工作已经发现,没有计划的预算或并不在项目范围内。管理储备可以提供该基金支付新发现的工作项。

  • 第21题:

    You are working on the cost budget for one project. Which of the following is true()

    • A、This process assigns cost estimates to project activities including risks and contingency plans.
    • B、The cost baseline will be used to measure variances and future project performance.
    • C、This process assigns cost estimates for expected future period operating costs.
    • D、The cost baseline is the expected cost for the project.

    正确答案:B

  • 第22题:

    Delay due to port congestion,pilots,tugs not available is a:()

    • A、Contingency;
    • B、Emergency;
    • C、A or B;
    • D、D.not A nor

    正确答案:B

  • 第23题:

    单选题
    You are working on the cost budget for one project. Which of the following is true()
    A

    This process assigns cost estimates to project activities including risks and contingency plans.

    B

    The cost baseline will be used to measure variances and future project performance.

    C

    This process assigns cost estimates for expected future period operating costs.

    D

    The cost baseline is the expected cost for the project.


    正确答案: C