单选题Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()A
Order a POW
题目
单选题
Company.com has recently received a new p5-570 in the data center and wants to Micro-Partition the server. The customer already has an existing HMC connected to a p690. Which of the following actions should the technical specialist take?()
A
Order a POWER5 HMC
B
Connect to the existing HMC
C
Install an 8-port asynchronous card in the managed server to connect to the existing HMC
D
Install an additional network card to the existing HMC and connect to the POWER5 service processor