单选题Which phase includes conducting Cisco Unified Communications network traffic analysis and capacity planning in order to ensure high availability()A DesignB PrepareC MaintainD Optimize

题目
单选题
Which phase includes conducting Cisco Unified Communications network traffic analysis and capacity planning in order to ensure high availability()
A

Design

B

Prepare

C

Maintain

D

Optimize


相似考题
更多“Which phase includes conducting Cisco Unified Communications”相关问题
  • 第1题:

    Which three products reside on the UC500 platform?()

    • A、Cisco Unified Communications ManagerExpress
    • B、Cisco IOS Firewall
    • C、Cisco UnifiedContact Center
    • D、Cisco IOS
    • E、Cisco Unity Express
    • F、Cisco UnifiedCallConnector

    正确答案:A,D,E

  • 第2题:

    Cisco Unified Communications 500 Series for Small Business, a critical part of the Cisco Smart Business Communications System, is a unified communications solution for small businesses that provides voice, data, voicemail. Which three features does the Cisco UC520 support?()

    • A、 distributed routing
    • B、 Cisco Unity Express
    • C、 security, firewall and VPN
    • D、 analog devices

    正确答案:B,C,D

  • 第3题:

    The final documentation that records detailed implementation information for customers, including specific design requirements, are delivered at which server component within the Cisco Unified Communications implement phase()

    • A、Project Closeout
    • B、As-Built Documentation
    • C、Operations Setup
    • D、Post-Implementation Support Handoff Meeting

    正确答案:B

  • 第4题:

    Which implement phase service component describes the activities to install and test your Cisco Unified Communications solution in a nonproduction lab environment()

    • A、Proof of Concept
    • B、Acceptance Testing
    • C、Staging
    • D、Lab Testing

    正确答案:C

  • 第5题:

    Which three deployment scenarios does Cisco Configuration Assistant support? ()

    • A、 Cisco SR 500 in secure router mode, acting as a front end for Cisco Unified Communications 500
    • B、 centralized Cisco Unified Communications Manager BE with Cisco Unified Communications 500 in SRST mode
    • C、 Cisco SR 500 teleworker with Cisco Unified Communications 500 as VPN server
    • D、 multi-site VPN with Cisco Unified Communications 500 platforms
    • E、 redundant Cisco Unified Communications 500 with primary-to-backup failover
    • F、 Cisco Unified Communications 500 to Cisco Unified Communications Manager SIP trunk

    正确答案:A,C,D

  • 第6题:

    Cisco Unified Communications 500 Series for Small Business, a critical part of the Cisco SmartBusiness Communications System, is a unified communications solution for small businesses that provides voice, data, voicemail. For which technology the Cisco UC520 provides integrated WLAN connectivity to mobile clients?()

    • A、 voice only
    • B、 data only
    • C、 data and voice
    • D、 None of above

    正确答案:B

  • 第7题:

    单选题
    Which Service component in Cisco Unified Communications operate phase identifies and solves reoccurring incidents by analyzing incident trends to identify patterns and systemic conditions()
    A

    Problem Management

    B

    Incident Management

    C

    Change Management

    D

    Systems Monitoring


    正确答案: D
    解析: 暂无解析

  • 第8题:

    单选题
    The final documentation that records detailed implementation information for customers, including specific design requirements, are delivered at which server component within the Cisco Unified Communications implement phase()
    A

    Project Closeout

    B

    As-Built Documentation

    C

    Operations Setup

    D

    Post-Implementation Support Handoff Meeting


    正确答案: D
    解析: 暂无解析

  • 第9题:

    单选题
    In which phase is the staff training development for Cisco Unified Communications planned()
    A

    Design

    B

    Implement

    C

    Plan

    D

    Prepare


    正确答案: A
    解析: 暂无解析

  • 第10题:

    单选题
    Which phase includes conducting Cisco Unified Communications network traffic analysis and capacity planning in order to ensure high availability()
    A

    Design

    B

    Prepare

    C

    Maintain

    D

    Optimize


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    Which phase and service component includes comparing the solution requirements with the bill of materials and high-level design in order to finalize the detailed business and technology requirements for the Cisco Unified Communications solution()
    A

    Plan - Application Readiness Validation

    B

    Prepare - Proof of Concept

    C

    Prepare - Technology Strategy Development

    D

    Plan - Systems Requirements Validation


    正确答案: B
    解析: 暂无解析

  • 第12题:

    单选题
    Which includes an activity to host a workshop that focuses on the identification and configuration of the actual network components (routers, servers, local-area network or LAN, and so on) that will be incorporated to run and support the Cisco Unified Communications system()
    A

    Implement

    B

    Design

    C

    Plan

    D

    Prepare


    正确答案: B
    解析: 暂无解析

  • 第13题:

    During the implement phase, systems acceptance testing provides which two of the following services for the customer()

    • A、It installs, configures, and verifies monitoring tools and processes in accordance with the operations implementation.
    • B、It verifies that the Cisco Unified Communications solutions is ready for production.
    • C、It verifies that the Cisco Unified Communications solution meets their business and technical requirements.
    • D、It executes and verifies the migration plan by migrating network services from an existing state to a future state.
    • E、It provides automated tools for measuring system performance under load.

    正确答案:B,E

  • 第14题:

    What customer benefits are provided by conducting a project kickoff in the Cisco Unified Communications plan phase()

    • A、It helps to confirm project roles and responsibilites, and milestones dates.
    • B、It reduces the risk of downtime caused by facilities-related problems.
    • C、It ensures that the customer receives a detailed network diagram.
    • D、It ensures end-user support immediately after the launch of the new system.

    正确答案:A

  • 第15题:

    You might recommend a Cisco Integrated Services Router to a business with which characteristic?()

    • A、 a high-bandwidth environment with applications such as IP video
    • B、 a predominantly telecommuter workforce
    • C、 a robust LAN intrusion detection system
    • D、 the intention to upgrade from Cisco Unified Communications Manager Express to Cisco Unified Communications Manager

    正确答案:A

  • 第16题:

    Which service component includes preparing for the Cisco Unified Communications customer demonstrations and presenting an overview of the applicable solutions()

    • A、Present an Overview of the Design
    • B、Conduct Administrator and End-User Trainging
    • C、Customer Educations
    • D、Proof of concept

    正确答案:C

  • 第17题:

    Which tool enables easy configuration and monitoring of Cisco ISRs? ()

    • A、Cisco MWAM
    • B、Cisco SDM
    • C、Cisco NAC Appliance
    • D、Cisco Unified Communications Manager Express

    正确答案:B

  • 第18题:

    单选题
    You might recommend a Cisco Integrated Services Router to a business with which characteristic?()
    A

     a high-bandwidth environment with applications such as IP video

    B

     a predominantly telecommuter workforce

    C

     a robust LAN intrusion detection system

    D

     the intention to upgrade from Cisco Unified Communications Manager Express to Cisco Unified Communications Manager


    正确答案: C
    解析: 暂无解析

  • 第19题:

    单选题
    Which phase includes testing operational processes and procedures in accordance with the Cisco Unified Communications operations plan()
    A

    Operate

    B

    Design

    C

    Deploy

    D

    Implement


    正确答案: B
    解析: 暂无解析

  • 第20题:

    单选题
    Which phase includes the activity of assisting the customer to monitor their Cisco Unified Communications system performance and to respond to trouble reports()
    A

    Maintain

    B

    Deploy

    C

    Operate

    D

    Optimize


    正确答案: A
    解析: 暂无解析

  • 第21题:

    多选题
    Which three deployment scenarios does Cisco Configuration Assistant support? ()
    A

    Cisco SR 500 in secure router mode, acting as a front end for Cisco Unified Communications 500

    B

    centralized Cisco Unified Communications Manager BE with Cisco Unified Communications 500 in SRST mode

    C

    Cisco SR 500 teleworker with Cisco Unified Communications 500 as VPN server

    D

    multi-site VPN with Cisco Unified Communications 500 platforms

    E

    redundant Cisco Unified Communications 500 with primary-to-backup failover

    F

    Cisco Unified Communications 500 to Cisco Unified Communications Manager SIP trunk


    正确答案: E,F
    解析: 暂无解析

  • 第22题:

    单选题
    Which service component in the plan phase evaluates the readiness of your current facilities infrastructure to support Cisco Unified Communications system development()
    A

    Network Readiness Assessment

    B

    Operation Readiness Assessment

    C

    Site Readiness Assessment

    D

    Application Readiness Assessment


    正确答案: C
    解析: 暂无解析

  • 第23题:

    多选题
    Which two of the following activities are included in the Cisco Unified Communications staff development()
    A

    Collect Cisco Unified Communications Training Materials

    B

    Develop Job Role Training Requirement

    C

    Request for Training Budget

    D

    Develop Curriculum Map

    E

    Develop Informal Basic Training


    正确答案: A,E
    解析: 暂无解析

  • 第24题:

    单选题
    Cisco Unified Communications 500 Series for Small Business, a critical part of the Cisco SmartBusiness Communications System, is a unified communications solution for small businesses that provides voice, data, voicemail. For which technology the Cisco UC520 provides integrated WLAN connectivity to mobile clients?()
    A

     voice only

    B

     data only

    C

     data and voice

    D

     None of above


    正确答案: A
    解析: 暂无解析