更多“Oil is carried in ().”相关问题
  • 第1题:

    A shipboard oil pollution emergency plan is required of ______.

    A.all vessels, regardless of size and commercial application

    B.any barge or other ship which is constructed or operated in such a manner that no oil in any form can be carried aboard

    C.an oil tanker of 150 gross tons or above, or other ship of 400 gross tons or above

    D.an oil tanker of 400 gross tons and above, or other ships of 150 gross tons and above


    正确答案:C

  • 第2题:

    Certificate of Fitness for the Carriage of Liquefied Gases in Bulk shall be carried on board by ______.

    A.gas carriers constructed on or after 1 July 1986

    B.gas carriers constructed before 1 July 1986

    C.All chemical tankers

    D.oil tankers of 150 gross tonnage and above


    正确答案:B

  • 第3题:

    Oil Record Book shall be carried on board by ______ which is engaged in voyages to ports or offshore terminals under the jurisdiction of other Parties to MARPOL 73/78.

    A.Oil tanker

    B.Bulk carrier of 400 gross tonnage and above

    C.Container vessel

    D.Passenger ship


    正确答案:B

  • 第4题:

    International Certificate of Fitness for the Carriage of Dangerous Chemicals in Bulk shall be carried on board by ______.

    A.chemical tankers constructed on or after 1 July 1986

    B.chemical tankers constructed before 1 July 1986

    C.All chemical tankers

    D.oil tankers of 150 gross tonnage and above


    正确答案:A

  • 第5题:

    Goods stowed in containers ______ without notice.

    A.Shall be carried on deck

    B.Shall be carried under deck

    C.May be carried on or under deck

    D.May not be carried on or under deck


    正确答案:C

  • 第6题:

    单选题
    The cooling of the piston is carried out by circulating () across the underside of the crown and inside the ring belt or through specially shaped passages.
    A

    sea water

    B

    scavenging air

    C

    lubricating oil

    D

    fuel oil


    正确答案: D
    解析: 暂无解析

  • 第7题:

    单选题
    A shipboard oil pollution emergency plan is required of ().
    A

    all vessels, regardless of size and commercial application

    B

    any barge or other ship which is constructed or operated in such a manner that no oil in any form can be carried aboard

    C

    an oil tanker of 150 gross tons or above, or other ship of 400 gross tons or above

    D

    an oil tanker of 400 gross tons and above, or other ships of 150 gross tons and above


    正确答案: A
    解析: 暂无解析

  • 第8题:

    单选题
    Goods stowed in containers()without notice.
    A

    shall be carried on deck

    B

    shall be carried under deck

    C

    may be carried on or under deck

    D

    may not be carried on or under deck


    正确答案: C
    解析: 暂无解析

  • 第9题:

    单选题
    In motor ship, () is often used to recover some of the heat carried in the exhaust gases from the main engine.
    A

    an diesel oil heater

    B

    a waste heat boiler

    C

    a fresh water generator

    D

    all the above


    正确答案: C
    解析: 暂无解析

  • 第10题:

    单选题
    Which of the following operating procedures should be carried out immediately after any diesel engine is started?()
    A

    Take all exhaust temperature reading

    B

    Check the sump oil level

    C

    Verify proper lube oil pressure

    D

    All of the above


    正确答案: C
    解析: 暂无解析

  • 第11题:

    单选题
    What monitoring device best indicates the load being carried by a diesel engine?()
    A

    Lube oil pressure gauge

    B

    Jacket water temperature gauge

    C

    Tachometer

    D

    Exhaust pyrometer


    正确答案: D
    解析: 暂无解析

  • 第12题:

    单选题
    In the case of new crude oil tankers,the additional ballast permitted shall be carried in cargo tanks only if such tanks have been()before departure from an oil unloading port or terminal.
    A

    inerted

    B

    crude oil washed

    C

    diluted

    D

    cleaned


    正确答案: B
    解析: 暂无解析

  • 第13题:

    In the case of new crude oil tankers,the additional ballast permitted shall be carried in cargo tanks only if such tanks have been ______ before departure from an oil unloading port or terminal.

    A.inerted

    B.crude oil washed

    C.diluted

    D.cleaned


    正确答案:B

  • 第14题:

    Certificate of insurance or other financial security in respect of civil liability for oil pollution damage shall be carried on board by ______.

    A.ships carrying more than 2000 tons of oil in bulk as cargo

    B.oil tankers

    C.bulk chemicals carriers

    D.liquefied gas carriers


    正确答案:A

  • 第15题:

    Shipboard Oil Pollution Emergency Plan shall be carried on board by ______.

    A.Oil tanker of 150 gross tonnage and above

    B.Bulk carrier

    C.Container vessel

    D.Passenger ship


    正确答案:A

  • 第16题:

    The port State control officer or the surveyor authorized by the port State Administration must be aware that ______ may be carried on product carriers.

    A.category A substances

    B.crude oil

    C.certain“oil like”noxious liquid substances

    D.category B,C and D substances


    正确答案:C

  • 第17题:

    The equipment required to remove an on-deck oil spill on a barge transfering oil must either be carried on board or ______.

    A.on a tug standing by

    B.available by contract with the shore facility

    C.kept at the shoreside hose connection during transfer

    D.kept in a protected shoreside location readily accessible


    正确答案:B

  • 第18题:

    单选题
    The port State control officer or the surveyor authorized by the port State Administration must be aware that()may be carried on product carriers.
    A

    category A substances

    B

    crude oil

    C

    certain“oil like”noxious liquid substances

    D

    category B,C and D substances


    正确答案: B
    解析: 暂无解析

  • 第19题:

    单选题
    A shipboard Oil Pollution Emergency Plan is required of().
    A

    all vessels,regardless of size and commercial application

    B

    any barge or ship constructed or operated in such a manner that no oil in any form can be carried aboard

    C

    an oil tanker of 150 gross tons and above,or other ship of 400 gross tons and above

    D

    an oil tanker of 400 gross tons and above,or other ships of 150 gross tons and above


    正确答案: A
    解析: 暂无解析

  • 第20题:

    单选题
    The pollution prevention regulations do not apply to the transfer or discharge of ()
    A

    bunker fuel for use aboard ship

    B

    lubricating oil for use aboard ship

    C

    coconut oil carried in tank vessels

    D

    oily water from a ships bilges


    正确答案: D
    解析: 暂无解析

  • 第21题:

    单选题
    () should be tested and adjusted when the boiler survey is carried out.
    A

    The boiler oil tank

    B

    The steam pipe

    C

    The fire side

    D

    The safety valves


    正确答案: D
    解析: 暂无解析

  • 第22题:

    单选题
    Preventive maintenance ().
    A

    should not be carried out during the watches

    B

    can only be carried out in port

    C

    is a kind of maintenances carried out prior to the occurrence

    D

    is a kind of maintenances carried out after the occurrence


    正确答案: B
    解析: 暂无解析

  • 第23题:

    单选题
    Following an overhaul of a crosshead type diesel engine, the engine is jacked over with the turning gear as part of the pre-start procedure, which of the listed pre-start procedures should be carried out?()
    A

    Ensure proper cylinder lube oil flow

    B

    Open all air space drain cocks

    C

    Open all indicator valves

    D

    all of the above


    正确答案: C
    解析: 暂无解析