  • 第1题:

    146 The planned cost for the total project at its inception is called the _____.

    A. Cost of goods sold.

    B. Depreciable value.

    C. Budgeted cost.

    D. All of the above.

    E. B and C only


    正确答案:C

  • 第2题:

    185 Life Cycle Costing:

    A. is the concept of including all costs within the total life of a project.

    B. is an activity devoted to optimizing cost/performance

    C. is an activity of appraising the cost and technical performance of a completed project.

    D. is a process of predicting the life of a project.

    E. None of the above


    正确答案:A

  • 第3题:

    The total cost in logistics in China is still higher than()in many other industrialized countries.

    A、it

    B、that

    C、those


    参考答案:B

  • 第4题:

    By default, which of the following factors determines the spanning-tree path cost?

    A.It is the individual link cost based on latency

    B.It is the sum of the costs based on bandwidth

    C.It is the total hop count

    D.It is dynamically determined based on load

    E.None of the above


    正确答案:B
    解析:Explanation:"TheSTPcostisanaccumulatedtotalpathcostbasedontheavailablebandwidthofeachofthelinks."Note:Apathcostvalueisgiventoeachport.Thecostistypicallybasedonaguidelineestablishedaspartof802.1d.Accordingtotheoriginalspecification,costis1,000Mbps(1gigabitpersecond)dividedbythebandwidthofthesegmentconnectedtotheport.Therefore,a10Mbpsconnectionwouldhaveacostof(1,000/10)100.Tocompensateforthespeedofnetworksincreasingbeyondthegigabitrange,thestandardcosthasbeenslightlymodified.Thenewcostvaluesare:Youshouldalsonotethatthepathcostcanbeanarbitraryvalueassignedbythenetworkadministrator,insteadofoneofthestandardcostvalues.IncorrectAnswers:A,D:TheSTPprocessdoesnottakeintoaccountthelatencyorloadofalink.STPdoesnotrecalculatethelinkcostsdynamically.C.HopcountsareusedbyRIProuterstocalculatethecostofaroutetoadestination.TheSTPprocessresidesatlayer2oftheOSImodel,wherehopcountsarenotconsidered.

  • 第5题:

    The (74) technique involves using project characteristics in a mathematical model to predict total project cost models Can be simple or complex.

    A.reserve analysis

    B.cost aggregation

    C.parametric estimating

    D.funding limit reconciliation


    正确答案:C

  • 第6题:

    总成本函数(Total cost function)


    正确答案: 总成本函数是指厂商的总成本和它的产量之间的关系。

  • 第7题:

    总成本(Total cost)


    正确答案: 总成本是一个厂商的总固定成本和总可变成本之和。

  • 第8题:

    By default, which of the following factors determines the spanning-tree path cost?()

    • A、It is the individual link cost based on latency
    • B、It is the sum of the costs based on bandwidth
    • C、It is the total hop count
    • D、It is dynamically determined based on load

    正确答案:B

  • 第9题:

    名词解释题
    总可变成本(Total variable cost)

    正确答案: 总可变成本是指每个时期厂商在可变投入品上的总支出。
    解析: 暂无解析

  • 第10题:

    名词解释题
    总固定成本〔Total cost)

    正确答案: 总固定成本是指每个时期厂商在不变投入品上的总支出。
    解析: 暂无解析

  • 第11题:

    问答题
    Room prices are regularly $100, but for each additional room rented by a group, the price is reduced by $3 for each room. For example, 1 room costs $100, 2 rooms cost 2× $97 = $194, 3 rooms cost 3 ×$94 = $282, and so on. What is the total cost of renting 6 rooms?

    正确答案: $510
    解析:
    由题干中的例子类推可知租六间房子的房租为6×[100-3×(6-1)] = 510。

  • 第12题:

    单选题
    No claim for constructive total loss based upon the cost of recovery and/or repair of the Vessel shall be recoverable hereunder unless such cost would exceed().
    A

    the stated value

    B

    the sound valve of the vessel at the time of occurrence

    C

    the lost value

    D

    the insured value


    正确答案: D
    解析: 暂无解析

  • 第13题:

    73 In a contract, the point of total assumption refers to the point where:

    A. The customer incurs the total financial responsibility for each additional dollar spent.

    B. The contractor incurs the total financial responsiblity for each dollar spent.

    C. The schedule and cost variance are zero.

    D. The customer will incur no further costs for the work the contractor performs in the completion of the contract.

    E. B and D only


    正确答案:E

  • 第14题:

    135 Using the cumulative cost curve in the special window, height B represents

    A. actual cost to date

    B. total budgeted costs for the project

    C. planned cost for month 6

    D. cost variance

    E. earned value


    正确答案:B

  • 第15题:

    From the functional income statement we can see clearly the total revenue, total cost and the gross profit etc.

    A.Right

    B.Wrong

    C.Doesn't say


    正确答案:C
    解析:文中只说it shows revenues less cost of goods sold (gross margin) less selling and administrative expenses,并没有说能看到"the total revenue, total cost"。

  • 第16题:

    The(7)technique involves using project characteristics in a mathematical model to predict total project cost. Models can be simple or complex.

    A.cost aggregation

    B.reserve analysis

    C.parametric estimating

    D.funding limit reconciliation


    正确答案:C
    解析:参数估算技术涉及在一个数学模型中利用项目特性来预测整体项目成本。模型可以是简单的也可以是复杂的。

  • 第17题:

    What is the maximum value (as a percentage of total cost) that an item identified as condition-coded can have?()

    • A、 25%
    • B、 50%
    • C、 75%
    • D、 100%

    正确答案:D

  • 第18题:

    总固定成本〔Total cost)


    正确答案: 总固定成本是指每个时期厂商在不变投入品上的总支出。

  • 第19题:

    总可变成本(Total variable cost)


    正确答案:总可变成本是指每个时期厂商在可变投入品上的总支出。

  • 第20题:

    Which of the following BEST describes the function of a redundant power supply?()

    • A、 Provides additional diagnostic LEDs
    • B、 Reduces power consumption
    • C、 Eliminates a single point of failure
    • D、 Reduces total cost of ownership

    正确答案:C

  • 第21题:

    名词解释题
    Cost,total总成本

    正确答案: 在某技术水平和要素价格条件下可以得到的最低成本的总额。现有工厂和其他不变成本既定的条件下所发生的成本为短期成本。而厂商在投人和决策方面一直有完全弹性的条件下所发生的成本则为长期总成本。
    解析: 暂无解析

  • 第22题:

    单选题
    Re-handling can save cost and improve service, Is it true or not? ()
    A

    Wrong

    B

    Not total true

    C

    True

    D

    Not clear here


    正确答案: C
    解析: 暂无解析

  • 第23题:

    问答题
    I bought four things this morning. The dictionary was 5 times the cost of the book, the tie was 30 times the cost of the book,the watch was 4 times the cost of the tie, and I spent 312 dollars in total. What was the price of the dictionary?

    正确答案: 10
    解析:
    假设字典的价格为x,那么书的价格为1/5x,领带的价格为30×1/5x,手表为4×30×1/5x,这些东西的总价值为312,因此可得方程式x+1/5x+30×1/5x+4×30×1/5x=312,故x=10。

  • 第24题:

    名词解释题
    总成本函数(Total cost function)

    正确答案: 总成本函数是指厂商的总成本和它的产量之间的关系。
    解析: 暂无解析