更多“Cost accounting analyzes a business's cost to help managers ______.A.expend moneyB.control expensesC.pay the debtsD.make budget”相关问题
  • 第1题:

    A negative cost variance and positive schedule variance means:

    A The project is under budget and ahead of schedule

    B The project is over budget and behind schedule

    C The project is over budget and ahead of schedule

    D The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第2题:

    114 The Cost Performance Index is computed as:

    A. budget cost of work performed divided by actual cost of work performed

    B. budget cost of work performed minus actual cost of work performed

    C. budget cost of work performed minus budget cost of work scheduled

    D. budget cost of work scheduled divided by budget cost of work performed

    E. actual cost of work scheduled divided by budget cost of work performed


    正确答案:A

  • 第3题:

    You are working on the cost budget for one project. Which of the following is true()

    A.This process assigns cost estimates to project activities including risks and contingency plans.

    B.The cost baseline will be used to measure variances and future project performance.

    C.This process assigns cost estimates for expected future period operating costs.

    D.The cost baseline is the expected cost for the project.


    参考答案:B

  • 第4题:

    ● The Work Breakdown Structure (WBS) is the basis for communicating:

    A Project scope, cost control, schedule, quality

    B Project objectives, dependencies, plan, cost control

    C Project scope, schedule, staffing, cost control

    D Project scope, quality, schedule, dependencies

    E Project budget, schedule, risk factors, work assignments.


    正确答案:A

  • 第5题:

    (b) Assuming that the cost of equity and cost of debt do not alter, estimate the effect of the share repurchase on the company’s cost of capital and value. (5 marks)


    正确答案:

    (b) Estimated new cost of capital:
    If equity is repurchased such that the gearing becomes 50% equity, 50% debt, the new estimated weighted average cost of capital is:

  • 第6题:

    The earned value technique is a commonly used method of performance measurement.It integrates project scope,schedule,and cost measures to help the project management team assess project performance.If a project’s Cost Performance Index(CPI=EV/AC)value less than 1.0,it means that( )。 A.the cost savings for work completed B.the project is ahead of its planned schedule C.the cost overrun for work completed D.1ess work was completed than was planned


    正确答案:C
    挣值管理(EVM)是一种常用的绩效测量方法。它综合考虑项目范围、进度与成本指标,帮助项目管理团队评估项目绩效。如果某个项目的成本绩效指数(CPI=EV/AC)值小于1.0,则说明已完成的工作的成本超支(the cost overrun for work completed)。

  • 第7题:

    The earned value technique is a commonlyused method of performance measurement. It integrates project scope, cost, andschedule measures to help the project management team assess projectperformance.If a project’s Schedule Performance Index(SPI=EV/PV) value less than 1.0, itmeans that (74).

    A.the project is ahead of its planned schedule

    B.less work was completed than was planned

    C.the cost overrun for work completed

    D.the cost under-run of performance to date


    正确答案:B
    此题主要考查挣值分析法的相关概念,它综合了范围、时间和成本数据,主要用于实际成本的绩效测量。基本思想是通过测量和计算已完成工作的预算费用与已完成工作的实际费用,将其与计划工作预算费用相比较得到项目的费用偏差,从而达到判断项目成本和进度计划执行情况,来帮助项目管理团队分析项目的完成情况,衡量项目的成本效率,为成本控制提供依据。挣值分析法主要涉及到3个参数,4个指标。其中3个参数如下:?计划工作量的预算成本(PV),已完成工作量的预算成本(EV),已完成工作量的实际成本(AC)?4个指标是指CV,SV,CPI,SPI:进度偏差(SV)是项目进度绩效的一种指标。成本偏差(CV)是项目成本绩效的一种指标。进度绩效指数(SPI)是比较项目已完成进度与计划进度的一种指标。当SPI小于1.0时,说明已完成的工作量未达到计划要求;当SPI大于1.0时,则说明已完成的工作量超过计划。SPI等于EV与PV的比值。公式:SPI=EV/PV。成本绩效指数(CPI)是比较已完成工作的价值与实际成本的一种指标。它考核已完成工作的成本效率。当CPI小于1.0时,说明已完成工作的成本超支;当CPI大于1.0时,则说明到目前为止成本有结余。CPI等于EV与AC的比值。公式:CPI=EV/AC。

  • 第8题:

    Activity Based Costing(ABC) is an(66)technique that allows an organization to determine the actual(67)associated with each product and service produced by the organization without regard to the organizational structure. This chapter explains some of the uses and benefits of Activity Based Costing. We use IDEFO(68)modeling in conjunction with ABC to enable more effective business(69) design decisions.In order to achieve the major goals of business process improvement, process simplifica- tion and improvement, FAA managers need to fully understand the cost, time, and quality of activities performed by employees or machines throughout an entire organization. ABC methods enable(70) to cost out measurements to business simplification and process improvement.

    A.computing

    B.campaigning

    C.programming

    D.accounting


    正确答案:D

  • 第9题:

    资料:As a business owner, it is vital that you understand and use advanced technologies. Technology can help increase business efficiency and even expand operations.
    Accounting software. This is important, even if you have your own accountant or bookkeeper. Accounting software allows you to see your profits and losses at a glance. It can also help you design and maintain a budget for your business.
    Planning software or tools. A calendar system is a must There are many online planning systems that can be utilized to help you keep your calendar organized. Find a system that meets your business' needs and be sure to stick with it
    Time tracking software. A time tracking device will help you determine what tasks result in a profit and what tasks do not. This will help you determine what tasks can be eliminated, outsourced, or improved. If you're looking at software that requires a fee, ask for a free trial first to make sure it's the right software for you.

    Email management As a business owner, you probably use several email accounts to manage the various aspects of your company. If you streamline these emails to one account, you'll be able to stay organized and abreast of your emails.
    Mobile internet access. Access to the internet on your mobile device will not only make your life easier, it will also help you maintain a positive reputation for your business. For example, if you are able to follow up with a client by email immediately after a meeting. you will be showing that you are accessible, timely and professional.
    Once you decide which types of technology are right for you and your business, you'll be on your way to being more organized and efficient than ever.

    What’s the author's attitude towards advanced technology?

    A.Negative
    B.Critical
    C.Positive
    D.Neutral

    答案:C
    解析:
    本题的问题是“作者对于先进技术的态度是什么?”。A选项“消极的”;B选项“批评的”;C选项“积极的”;D选项“中立的”。根据主题句可知,作者对于先进技术持积极态度,故选C。

  • 第10题:

    英译中:Accounting cost


    正确答案: 会计成本

  • 第11题:

    Saving or reducing expenditure in business is()

    • A、save money
    • B、increase cost
    • C、cost planning
    • D、cost control

    正确答案:D

  • 第12题:

    单选题
    You are working on the cost budget for one project. Which of the following is true()
    A

    This process assigns cost estimates to project activities including risks and contingency plans.

    B

    The cost baseline will be used to measure variances and future project performance.

    C

    This process assigns cost estimates for expected future period operating costs.

    D

    The cost baseline is the expected cost for the project.


    正确答案: B
    解析: 暂无解析

  • 第13题:

    65 Which of the following is referred to as sunk cost:

    A. management reserve

    B. contingency fund

    C. cost budgeted for construction under water

    D. expended funds over which there is no further control

    E. forecasted budget over-runs


    正确答案:D

  • 第14题:

    72 Project trade-offs vary between

    A. risk, cost and schedule.

    B. direct cost, indirect cost, and resource availability

    C. quality, schedule and time

    D. cost, quality and schedule

    E. contract terms, scope and budget


    正确答案:D

  • 第15题:

    96 A negative cost variance and positive schedule variance means:

    A. The project is under budget and ahead of schedule

    B. The project is over budget and behind schedule

    C. The project is over budget and ahead of schedule

    D. The project will be overrun but ahead of schedule at completion


    正确答案:C

  • 第16题:

    ● In order to achieve the major goals of business process improvement, process simplification and improvement, FAA managers need to fully understand the cost, time, and quality of activities performed by employees or machines throughout an entire organization. ABC methods enable () to cost out measurements to business simplification and process improvement. () A. computers B. managers C. clients D. consumers


    正确答案:B
        为了达到业务流程改进、过程简化和改进的主要目的,FAA经理们需要充分理解那些由员工或机器执行的、贯穿整个组织的活动的成本、时间和质量。ABC法能让经理们估算出度量业务简化和过程改进的成本。

  • 第17题:

    (b) The CEO of Oceania National Airways (ONA) has already strongly rejected the re-positioning of ONA as a ‘no

    frills’ low-cost budget airline.

    (i) Explain the key features of a ‘no frills’ low-cost strategy. (4 marks)


    正确答案:
    (b) (i) A ‘no frills’ strategy combines low price with low perceived benefits of the product or service. It is primarily associated
    with commodity goods and services where customers do not discern or value differences in the products or services
    offered by competing suppliers. In some circumstances the customer cannot afford the better quality product or service
    of a particular supplier. ‘No frills’ strategies are particularly attractive in price-sensitive markets. Within the airline sector,
    the term ‘no frills’ is associated with a low cost pricing strategy. In Europe, at the time of writing, easyJet and Ryanair
    are the two dominant ‘no frills’ low-cost budget airlines. In Asia, AirAsia and Tiger Airways are examples of ‘no frills’ lowcost
    budget carriers. ‘No frills’ strategies usually exist in markets where buyers have high power coupled with low
    switching costs and so there is little brand loyalty. It is also prevalent in markets where there are few providers with
    similar market shares. As a result of this the cost structure of each provider is similar and new product and service
    initiatives are quickly copied. Finally a ‘no frills’ strategy might be pursued by a company entering the market, using thisas a strategy to gain market share before progressing to alternative strategies.

  • 第18题:

    - Looking at this, if my calculations are correct, we are about five thousand dollars over budget. - That's right.__________.

    A It will cost about eight percent more than initially projected ;

    B We will need another four thousand dollars to cover the cost ;

    C It's going to cost about five thousand more to complete the first order


    参考答案:C

  • 第19题:

    ( )is the approved version of the time-phased project budget,excluding any management reserves,which can only be changed through formal change control precedures and is used as a basis for comparison to actual results.

    A.The control accounts

    B.Funding requirement

    C.The cost estimates

    D.The cost baseline


    正确答案:D

  • 第20题:

    The earned value technique is a commonly used method of performance measurement. It integrates project scope, cost, and schedule measures to help the project management team assess project performance. If a project’s Schedule Performance Index(SPI=EV/PV) value less than1.0, it means that_().

    A.the project is a head of its planned schedule
    B.less work was completed than was planned
    C.the cost overrun for work completed
    D.the cost under-run of performance to date

    答案:B
    解析:
    挣值技术是一种综合了范围、成本、进度指标的绩效测量方法,帮助项目团队评价项目绩效。如果一个项目的进度绩效指数SPI值小于1,意味着:(74)A.项目滞后B.项目超前C.项目超支D.成本有结余

  • 第21题:

    You are working on the cost budget for one project. Which of the following is true()

    • A、This process assigns cost estimates to project activities including risks and contingency plans.
    • B、The cost baseline will be used to measure variances and future project performance.
    • C、This process assigns cost estimates for expected future period operating costs.
    • D、The cost baseline is the expected cost for the project.

    正确答案:B

  • 第22题:

    Saving or reducing expenditure in business is ()

    • A、Save money  
    • B、Increase cost  
    • C、cost planning  
    • D、cost control

    正确答案:D

  • 第23题:

    名词解释题
    英译中:Accounting cost

    正确答案: 会计成本
    解析: 暂无解析